Permanent Campus

  1. Home
  2. /
  3. Permanent Campus

Permanent Campus of IIM Bodh Gaya

About Permanent Campus

IIM Bodh Gaya is functioning from its transit campus from the B.Ed. Building of Magadh University, suitably modified. However, the construction of its permanent campus is in full swing and is likely to be completed by the March 2023.

On finalisation of design and drawing, CPWD floated an open Tender on July 14, 2020, “Name of Work: Construction of Permanent Campus of Indian Institute of Management (IIM) Bodhgaya, Bodhgaya, Bihar. Phase-I SH- Construction of Academic block, MDP Education, MDP Residence, Auditorium, Sports Complex, Hostel, Mess, Professor’s Residence, Assistant Professor’s Residence, Staff Housing, Director Bungalow, Servant quarters, Medical Centre, Utility block including Civil, Electrical & Mechanical and Horticulture Works/Services/ External Developments works, Roads, Pathway, sculpture, signage, internal and external electrical installations, Fire Fighting, Fire Alarm, Lifts, Substations, DG Sets, HVAC, LAN Networking, IBMS, AUDIOVISUAL SYSTEM, Solar Photovoltaic Panel, STP, WTP etc. on EPC Basis.

The construction of the permanent campus commenced on September 2020, and is likely to be completed by the March 2023.

Proposed Campus

Walkthrough of Proposed Campus

Campus Inauguration

Emotions ran high as we celebrated the long-awaited inauguration of our campus! It was a day of togetherness and hard work paying off. Check out the glimpses of the eventful day!

Campus Construction Progress as on Feb-2024

Current Status of Campus

Campus Construction Progress as on January-2024

Current Status of Campus

Campus Construction Progress as on December-2023

Current Status of Campus

Campus Construction Progress as on October-2023

Current Status of Campus

Campus Construction Progress as on September-2023

Current Status of Campus

Campus Construction Progress as on August-2023

Current Status of Campus

Campus Construction Progress as on July-2023

Current Status of Campus

Campus Construction Progress as on June-2023

Current Status of Campus

Campus Construction Progress as on May-2023

Current Status of Campus

Campus Construction Progress as on April-2023

Current Status of Campus

Campus Construction Progress as on March-2023

Current Status of Campus

Campus Construction Progress as on Feb-2023

Current Status of Campus

Campus Construction Progress as on Jan-2023

Current Status of Campus

Campus Construction Progress as on Dec-2022

Current Status of Campus

Campus Construction Progress as on Nov-2022

Current Status of Campus

Academic-Block-Side-View

Image 2 of 14

Campus Construction Progress as on April-2022


Campus Construction Progress as on December-2021

Permanent Campus Walkthrough


Proposed Campus


Walkthrough of Proposed Campus


   

 

IIMBG Footer